Hanoi steps up progress of key projects

Hanoi is speeding up progress on several key projects, according to the municipal People’s Committee.

img-262
Illustrative image (Photo: hanoimoi.com.vn)

Hanoi (VNA) – Hanoi is speeding up progress on several key projects, according to the municipal People’s Committee.

They include the 12.5km Nhon-Hanoi Station railway project, which is over three quarters completed, the Belt Road 2 section of Vinh Tuy Bridge – Nga Tu So, the second stage of Vinh Tuy Bridge, the Hanoi Children’s Palace, and the Le Van Luong Underpass No.3.

In August, State capital disbursement in Hanoi was estimated at nearly 4.2 trillion VND (179.3 million USD), up 1.8% monthly and 2.2 times from the same period last year. On an eight-month calculation, the figure rose by 8.5% annually to 27.9 trillion VND, or 54.7% of the 2022 plan.

Municipal authorities have asked districts and investors to promptly report progress of projects and deal with any difficulties facing them./.

Source: vietnamplus.vn


Lastest News

Progress Update of Oriental Square Grade A Office Building – December 6, 2024

2026.12.06

Progress Update of Oriental Square Grade A Office Building - November 21, 2024

2024.11.21

Oriental Square Wins Double Honors at PropertyGuru Vietnam Property Awards

2024.11.15

Construction Update: Oriental Square Grade A Office Building as of November 1, 2024

2024.11.01

CELEBRATING VIETNAMESE WOMEN'S DAY – OCTOBER 20, 2024

2024.10.20

OSI Holdings Supports Bac Tu Liem District Disaster Prevention Committee with 13 Emergency Fi

2024.09.10

OSI Holdings Organizes Project Implementation Seminar Combined with Team-building in Tam Coc,

2024.08.11

OSI Holdings Completes BIM and Revit Architecture Training Program

2024.07.11

Year-End Party 2023 and New Year 2024 Celebration of OSI Holdings

2024.01.26

Groundbreaking Ceremony for the Oriental Square Project at Starlake

2024.01.26
26

PAGE TOP